Tech Portal
The My Schedule screen of the Technician portal will now sort the tasks and display them based on the task priority and equipment criticality.
Example:
- Task 1 - Priority 1, Criticality 1
- Task 2 - Priority 1, Criticality 2
- Task 3 - Priority 1, Criticality 3
- Task 4 - Priority 2, Criticality 1
- Task 5 - Priority 2, Criticality 2 and goes on
Tasks should be sorted left to right, top to bottom.
Planner Portal
Tasks must have at least one skillset in order to be considered "planned." The planning wizard will not allow a task to be considered planned (and able to be moved to Period Capacity) without a skill set attached to it.
Training Documentation: | How do I add skill sets to a Job Plan in the Planner Portal?
We will be rolling out additional Planner Portal functionality in the upcoming weeks. Our next release is tentatively scheduled for 3/8/2022.