Steps in the screenshots correspond to the numbers in the headings.
As long as it still says "NEW PART" on the Task, in both the CLIENT and the Work Module, the SCS can go into the CLIENT and change the location of the Part Need.
This does NOT change the location on the Escalation, but that does not matter. As the Requisition will be kicked off from the Task, this should not be a concern.
1. The Tech enters the New Part request in the Work Module. All information is entered in the pop-up window.
Location is not one of the things that can be edited in the Portal, only Quantity and Due Date. The Tech could, however, DELETE this Part Need and re-enter it with the proper location. Or, s/he can follow the steps below.
0 Comments