7.15 How does the Copy Job Plan functionality work in the Planner Portal?

Updated on

Steps in the screenshots correspond to the numbers in the headings.

1. Go to the Planner Scheduler role to enter the Planner Portal.

2. Click on Job Plans.

3. Click on the double plus sign icon.  This is how you begin the copy process.

4. The Copy Job Plans screen loads.  It takes a few seconds to populate, because it is loading all of the job plans currently in existence.

5. The screen is split in half.  

6. On the left side are all the available job plans for you to copy.  It is from this side that you will do all the selecting.

7. Please note that the headers listed are Job Plan ID, Site, and Description.

8. The filter or funnel icon is where you begin to narrow your selection.  You can do this a number of times until you have selected just the plans you want to copy.

9. In the middle of the screen are the Add and Remove buttons which will allow you to copy the Job Plans to your specific site.

10. Click on the funnel to bring up the table filters.  Multiple filters can be applied at the same time.

eFactoryPro - Planning - Google Chrome

10.1. The Job Plan ID is a searchable field.  Your options are Starts with, Ends with, Equals and Contains.  

10.2. Site options are the same:  Starts with, Ends with, Equals and Contains.  The site number field is a four-digit number.

You can only copy one field at a time.  For example, you cannot combine words (like if you wanted to see all the Quarterly Crane PMs, you could not use Contains with Cranes and Quarterly.)  You could, however, combine description of Cranes with a manufacturer or a model filter.

10.4. Master Job Plan allows you the ability to select if you want to see Master Job Plans or not.

10.5. Model is used in a similar capacity.  A good example is you just got a new FINNPOWER Punch Press at your site - Model Finnpower Crimping Products (Hydrapower Dynamics Ltd) TRS6SB.  You could use the Model filter, and choose Contains and type TRS6SB to see if there are any Job Plans that are associated with that machine

10.6. Another option would be to use the Manufacturer filter and select Starts with Finn, or to use a combination of the two.

10.7. Asset ID would be applicable if you are using site-specific job plans and you want to see plans that you know have equipment tied to them.  Filter options include Starts With, Ends with, Equals and Contains.

10.8. Click Apply to execute the search and see your results.

If you want to change the results, you can click the Cancel or Clear buttons.

11. It is important to understand how the Asset ID, Model and Manufacturer work.  Keeping with the example started in 11.6, Site 0493 just got a new Finnpower Crimper.  I know that Site 0636 has Finns so I bring up the filter and enter our examples.

However, because none of the job plans actually have the equipment tied to the Job Plan, if you tried to add a manufacturer field, you will see zero results.

eFactoryPro - Planning - Google Chrome

12. Find the Job Plans that you wish to copy and click the checkbox to select.

13. If you wish to copy all of them, you can simply click the "Select Page" icon above the Job Plan ID.

In our example, we are going to copy all the ones that say Finnpower in the name.

14. The Add button in the Center becomes Active.

15. Click the Add button and the selected job plans are moved over to the right panel.

If you decide you don't want to copy one of them, you can simply check the box and choose the remove box to remove it from the list.

16. Click the COPY AS SITE JOB PLAN button to complete the Copy.

17. A message in the upper right corner tells you that copying is in process.

18. Confirmation messages tell you that the Job Plans created successfully and gives you the new job plan numbers.

The new Job Plans will be created with your site's default team (the one that ends with -ATS).

If any hyperlinks are attached to the original Job Plan, they will be copied over as well.  You can delete them if you do not feel they are applicable to your site.

Please note:  If there are parts attached to any of the job plans, they WILL be copied over as Staged Parts, with your site's default receiving location.  This can be changed in the editing process.

19. Click OK.

Snagit Editor - [Feb 27, 2020 3:58:45 PM]

20. You will be returned to the Job Plan Grid in the Site Job Plan Only view.

21. From here, you can click on the three dot icon to edit the Job Plan, add equipment, add attachments, etc.

Unless you are copying from within your site, skillsets do not copy over, and a required on every Job Plan, so make sure that you choose Edit Job Plan and add the required skillset that is appropriate for your site. If you want the skillsets to copy over it will only happen from copying from one site to the same site.

Example:

From 626 to 202 will NOT copy the skill sets. From 202 to 202 WILL copy skillsets.

0 Comments

Add your comment

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Previous Article 7.14 JOB PLAN: As an Admin, how can I create Master Job Plans in the Planner Portal?
Next Article 7.16 What shows up on the Job Plan History Screen in the Planner Portal?