In Q3 2021, the scheduling portion of Work Execution Management will be released in the Planner Portal.  At that time, all scheduling work should be done in the Planner Portal: Planning (efactorypro.com)

1. The Schedule Board defaults to the Timeline view, which shows the team on the left side and the calendar on the right.

2. To change to a weekly view and schedule a single Technician for the entire week at a time, click on the Week view in the middle of the header.

Click and drag the Tasks up from the bottom to schedule as usual.

A video on this topic can be found by clicking the following link:

0 Comments

Add your comment

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Previous Article 15.4 How do I increase the duration of a task on the Schedule Board in the CLIENT?
Next Article 15.6 How do I see a weekly/monthly schedule for a tech in the Schedule Board in the CLIENT?