The easiest way to begin is to have a spreadsheet with all the overdue PMs that you need to cancel. You can get this from the Portal.
3. Select the Tables Filters button.
4. Scroll down to Compliance Finish.
5. Enter the date range of the PMs you would like to cancel.
In this example we will use DATE instead of OFFSET.
7. The grid will now populate with open PM whose Compliance Dates fall within the chosen date. The total number of tasks will been shown at the top.
From here each task will need to be selected and the status of CANCELED will need to be manually changed.
8. To change a status to Canceled the user will first select the Task line.
10. From the Status drop down select Canceled.
12. The Task is now Canceled.
If you have PM tasks to cancel, you will still have to go to the Work Module task grid and cancel them individually.
It's also worth mentioning that PM that are marked as INACTIVATED in the Planner Portal will NOT regenerate in the future. This will greatly reduce the need for mass cancellations of PMs.