eFactoryPro Wiki

7.4 How do Operator Performed Maintenance PMs affect my Compliance/Completion Metrics?

Updated on

Essential Resources: To complete this training you must have access to eFACTORYPRO.

In a word - they don't.  Anything PM marked as Operator Performed is not considered in the standard ATS PM Compliance.

Steps in the screenshots correspond to the numbers in the headings.

1. In order to be considered as "OPM", Operator Performed must show under Sub-Types in the Job Plan in the Planner Portal.

2. Or in the Portal, the Task Activity Sub-Type must say Operator Performed on the Task Summary Screen.

  • It works best if you assign a Customer Team in conjunction with any Operator Performed work. 
  • This team should have the "External Team" checkbox marked.  
  • This makes it easy for the Planner Scheduler to separate out these PMs, print them out, and give them to the customer, and easier to find them to enter time and close them when the work is done.

0 Comments

Add your comment

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Previous Article 7.3 How do I create a Job Plan for Operator Performed PMs?
Next Article 7.5 How do I mark a Job Plan as Regulatory?